Control and supervision of 63 KV line laying works for the SBEE

Country : Benin. .
Client : SBEE - Société Béninoise d’Energie Electrique
Start Date : 2022-03-01
Completion Date : 2022-06-30
Value of services : 18 650 EUR
Funder : SBEE - Société Béninoise d’Energie Electrique
Associate/Partner : N/A
   ---------------------------------------------------------------------------------------------------------------------------------
Description :
The service, carried out in the suburbs of Cotonou in Benin, covers the monitoring of the works to be carried out by the Bouygues company to move the Calavi-Cococodji 63kV link to Akassato over 1.7 km. The construction of a market (private domain) requires the relocation of the cable for intervention constraints (operation and maintenance) on the network built in this area.
   ---------------------------------------------------------------------------------------------------------------------------------
Description of the Actual Services Provided • Review of the implementation studies carried out by Bouygues Energie service
• The weekly follow-up of the work by our local teams including the reception of the picket of the works and a displacement of 1/2D per week during the execution of the work to validate the progress of the work, control the quality of the works, remove any constraints.
• The presence of an international expert at the testing and acceptance of the line

Main deliverables:
- Weekly photo reports during the works execution
- A final report following the commissioning and acceptance of the works