Technical assistance
Power transmission. Rural electrification N/A
Improving Access to Electricity in Senegal (PADAES)
Country : | Senegal. . |
Client : | SENELEC |
Start Date : | 2023-11-01 |
Completion Date : | 2026-10-31 |
Value of services : | 3 439 018 EUROS |
Funder : | World Bank . |
Associate/Partner : | N/A |
--------------------------------------------------------------------------------------------------------------------------------- | |
Description : |
The consultant provides the services of Consulting Engineer for the control and supervision of the distribution networks construction works in the North part of Senegal (Dakar Regions; DRCO: Thiès and Diourbel; DRN: Saint Louis, Louga and Matam) through the following components: - Component 1: Extension and densification of the MV/LV distribution network: 438 MV/LV substations, 389 km of MV network, 1279 km of LV networks, approximately 100,000 connections - Component 2: Access to electricity for a resilient and inclusive post-Covid recovery: 18,400 indoor installations for vulnerable households, 360 connections for essential public services (health centre and school), 350 connections for micro, small and medium-sized companies |
--------------------------------------------------------------------------------------------------------------------------------- | |
Description of the Actual Services Provided | Mission 1: Handling of the pre-project study, tender documents and support for the procurement (estimated duration: 6 months): • Perform proofreading of APDs and DAOs; • Assist the project owner and the lessor in the awarding of contracts for the contractors selection process; Mission 2: works and services control and follow-up (estimated duration: 30 months) • To administratively and financially monitor the Manufacturers' contracts; • To monitor the technical and quantitative execution of the work carried out by the Builders; • To control the quality of the materials, equipment and work carried out by the Manufacturers; • To supervise operational commissioning, partial, provisional and final acceptances; • To ensure that the Builders take into account environmental and social considerations during the work; • To monitor and supervise the implementation of the ESMP by the Manufacturers; • Ensure the monitoring and implementation of the ICP • To develop, carry out and coordinate social intermediation activities and commercial animation • To carry out capacity building with the Client |