Demand forecast, electrical connection options and HV grid integration study for the Mungo Falls hydroelectric power plant project (95MW)

Country : Cameroon. .
Client : Berkeley Energy Cameroon (BEC)
Start Date : 2024-12-01
Completion Date : 2024-12-31
Value of services : 55 926 EUROS
Funder : Berkeley Energy Cameroon (BEC)
Associate/Partner : MasterGrid – Power Grid Modeling
   ---------------------------------------------------------------------------------------------------------------------------------
Description :
Berkeley Energy Cameroon (BEC) is a private investor wishing to develop the Mungo Falls hydroelectric power plant project in Cameroon (95MW) as an IPP. He wishes to justify the relevance of the project to national decision-makers, to know the method and cost of connection as well as the possibility of integrating the project into the existing HV electricity network.
   ---------------------------------------------------------------------------------------------------------------------------------
Description of the Actual Services Provided The service is as follows:
- Forecast of Cameroon's energy demand from 2029 to 2035. Analysis of current projects and estimation of production capacities. Supply/demand balance
- Regional Network Incident Analysis
- Grid Code Analysis
- Study and costing of the different options for connection to the existing HVB network in 90kV and 225kV
- Study of a 30kV MV line branch
- Regional Power Grid Modeling and Simulation of Integration Options for Mungo Falls Generating Station (95MW)
- Analysis of the results and synthesis of the impacts and beneficial effects of the plant for the improvement of the national network and the quality of service.