Consultancy
Power transmission. Power distribution  N/A

barre-colore

 

Consulting engineer for the supervision of the construction works of 60 kilometers of lines and extension of 225KV substations between EDEA and DOUALA

Country : Cameroon. .
Client : SONATREL
Start Date : 2025-01-22
Completion Date : 2027-12-31
Value of services : 1 573 107 EUROS
Funder : World Bank .
Associate/Partner : ARTELIA
   ---------------------------------------------------------------------------------------------------------------------------------
Description :
The consultant provides consulting engineer services for the control and supervision of the construction works of the 225KV double-circuit line between the EDEA BEON substation and the cut-off entry on the MISSOLE substation (DOUALA).

The work consists of the construction of a 225 kV electricity transmission line with a length of about 60 km with the removal of an existing line over 35 km. This work also includes the extension of two spans in the existing EDEA BEON substation and the resumption of control work in the existing MISSOLE and NGODI BAKAKO substations.
   ---------------------------------------------------------------------------------------------------------------------------------
Description of the Actual Services Provided The consultant's services include all the activities of control and supervision of the works and assistance during the warranty period, including:

• Supervision and control of detailed engineering studies, execution and works:

o Validation of execution studies
o Participation in FATs (factory acceptance)
o Participation in SATs (site reception)
o Daily monitoring of the work (verification and validation of work permits, control and validation of acceptance reports)
o Project management assistance
o Assistance with contract management

• Monitoring the implementation of the Environmental and Social Management Plan (ESMP) and the Resettlement Action Plan (RAP);
• Validation of the compliance, tests effectiveness and results and structures commissioning ;
• Preparation of project progress and completion reports;
• Support during the warranty period;
• Reporting all its activities to the Director of the PMU;